WORKDAY returns the date that is a number of working days before or after a start date, skipping weekends and holidays.

Syntax

=WORKDAY(start_date, days, [holidays])
Argument What it means
days Working days to add (negative to go back).
holidays Range of holiday dates.

Examples

Example 1

=WORKDAY(A2, 5, Holidays)

Delivery date 5 working days after the order.

Example 2

=WORKDAY.INTL(A2, 5, 11, Holidays)

Same with a Sunday-only weekend.